2025 Street Improvements Project

Project Update No. 6 – 4/18/2025

2025 Street Improvements Project

  • Sanitary sewer replacement is complete.
  • Black Hills Energy has completed the new gas main installation and services have all been connected. 
  • The concrete patch in Center Avenue has been poured through the mainline.  The patch at the NE corner of the intersection where Black Hills tied-in and disconnected the old gas main will be poured at a later date.
  • Sanitary service verification/replacement will continue in 100 block of 1st Street SE early next week.
  • Water services on 1st Avenue SE will be connected to the new main next week.
  • After water & sewer service work is complete for the 100 block of 1st Street & 1st Avenue SE  storm sewer installation will commence. 
  • If any property owner along 1st Street SE has a recent sewer service televising video/report that shows their service is PVC please share this information with City Hall.